Assessment Year | 1986 |
---|---|
Principal Product | MACHINERY TO MAKE BOXES |
NAICS |
n/a
|
SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 347 |
Plant Area |
n/a
|
Annual Production | 36
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $257,267 | 4,633,646 |
kWh
|
$0.056 |
Natural Gas | $68,538 | 10,804 |
MMBtu
|
$6.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,988 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,577 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,320 | $300 |
$5,320
95,838
kWh
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,188 | - |
$1,188
21,395
kWh
|
- | - | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,113 | $4,000 | - |
$3,090
-
MMBtu
|
$23 | |
04 | 2.7261: Install timers and/or thermostats | $14,588 | $4,000 | - |
$14,588
-
MMBtu
|
- | |
05 | 2.1123: Install automatic stack damper | $2,110 | $6,020 | - |
$2,110
-
MMBtu
|
- | |
06 | 2.7226: Use computer programs to optimize hvac performance | $4,464 | $6,000 |
$4,464
80,305
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,785 | $1,776 |
$2,785
50,117
kWh
|
- | - | |
08 | 2.6121: Reduce hot water temperature to the minimum required | $420 | - | - |
$420
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $33,988 | $22,096 |
$13,757
247,655
kWh
|
$20,208
-
MMBtu
|
$23 | ||
TOTAL IMPLEMENTED | $27,577 | $12,076 |
$12,569
226,260
kWh
|
$15,008
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs