Assessment Year | 1985 |
---|---|
Principal Product | PAINT ADDITIVES |
NAICS |
n/a
|
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
n/a
|
Annual Production | 2,400,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $143,950 | 1,772,861 |
kWh
|
$0.081 |
Natural Gas | $6,363 | 869 |
MMBtu
|
$7.32 |
Fuel Oil #4 | $292,851 | 49,550 |
MMBtu
|
$5.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $58,080 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $53,109 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #4 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,948 | $358 |
$1,948
24,033
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,018 | $200 |
$4,018
49,531
kWh
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,803 | - |
$1,803
22,274
kWh
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $488 | $60 |
$488
6,155
kWh
|
- | - | - | |
05 | 2.4227: Use compressor air filters | $1,141 | - |
$1,061
13,189
kWh
|
- | - | $80 | |
06 | 2.4133: Use most efficient type of electric motors | $123 | $720 |
$123
1,465
kWh
|
- | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $511 | $240 |
$511
6,448
kWh
|
- | - | - | |
08 | 2.2437: Recover waste heat from equipment | $3,777 | $1,750 | - |
$3,777
-
MMBtu
|
- | - | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $195 | $21 | - |
$195
-
MMBtu
|
- | - | |
10 | 2.6121: Reduce hot water temperature to the minimum required | $371 | - | - |
$371
-
MMBtu
|
- | - | |
11 | 2.2135: Repair and eliminate steam leaks | $31,090 | $500 | - | - |
$31,090
-
MMBtu
|
- | |
12 | 2.1233: Analyze flue gas for proper air/fuel ratio | $11,719 | $537 | - | - |
$11,719
-
MMBtu
|
- | |
13 | 2.2136: Install / repair insulation on steam lines | $896 | $517 | - | - |
$896
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $58,080 | $4,903 |
$9,952
123,095
kWh
|
$4,343
-
MMBtu
|
$43,705
-
MMBtu
|
$80 | ||
TOTAL IMPLEMENTED | $53,109 | $2,832 |
$8,953
110,492
kWh
|
$371
-
MMBtu
|
$43,705
-
MMBtu
|
$80 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #4 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs