Assessment Year | 1985 |
---|---|
Principal Product | DYE PROD. INTERMEDIATES |
NAICS |
n/a
|
SIC | 2865: Cyclic Organic Crudes and Intermediates, and Organic Dyes and Pigments |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
n/a
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 5,640
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $204,869 | 2,655,041 |
kWh
|
$0.077 |
Natural Gas | $276,081 | 54,846 |
MMBtu
|
$5.03 |
Fuel Oil #4 | $45,698 | 7,920 |
MMBtu
|
$5.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $72,662 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #4 Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,962 | $525 |
$2,962
38,394
kWh
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $452 | $182 |
$452
5,862
kWh
|
- | - | |
03 | 2.2136: Install / repair insulation on steam lines | $2,594 | $8,405 | - |
$2,223
-
MMBtu
|
$371
-
MMBtu
|
|
04 | 2.2437: Recover waste heat from equipment | $2,045 | $1,600 | - |
$1,755
-
MMBtu
|
$290
-
MMBtu
|
|
05 | 2.2136: Install / repair insulation on steam lines | $4,470 | $8,786 | - |
$3,833
-
MMBtu
|
$637
-
MMBtu
|
|
06 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $20,887 | $49,937 | - |
$17,917
-
MMBtu
|
$2,970
-
MMBtu
|
|
07 | 2.7224: Reduce space conditioning during non-working hours | $1,460 | - | - |
$1,252
-
MMBtu
|
$208
-
MMBtu
|
|
08 | 2.7441: Replace broken windows and/or window sash | $13,972 | $1,211 | - |
$11,986
-
MMBtu
|
$1,986
-
MMBtu
|
|
09 | 2.2135: Repair and eliminate steam leaks | $23,820 | $160 | - |
$20,427
-
MMBtu
|
$3,393
-
MMBtu
|
|
TOTAL RECOMMENDED | $72,662 | $70,806 |
$3,414
44,256
kWh
|
$59,393
-
MMBtu
|
$9,855
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #4 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs