ITAC Assessment: ST0015
ITAC logo
ITAC Assessment: ST0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product TITANIUM PRODUCTS
NAICS
n/a
SIC 3356: Rolling, Drawing, and Extruding of Nonferrous Metals, Except Copper and Aluminum
Sales Range $5
M
to 10
M
# of Employees 177
Plant Area
n/a
Annual Production 2,000,000
lb
Production Hrs. Annual 4,675
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,757 839,977
kWh
Natural Gas $19,146 2,997
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,273 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,491

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,216 $1,229 $2,216
24,619
kWh
-
02 2.6121: Reduce hot water temperature to the minimum required $828 - $645
7,034
kWh
$183
-
MMBtu
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $581 $370 $825
9,086
kWh
$(-244.0)
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $180 $120 $180
2,052
kWh
-
05 2.2437: Recover waste heat from equipment $1,280 $500 - $1,280
-
MMBtu
06 2.7261: Install timers and/or thermostats $4,844 $1,000 - $4,844
-
MMBtu
07 2.7447: Install vinyl strip / high speed / air curtain doors $359 $41 - $359
-
MMBtu
08 2.3191: Use demand controller or load shedder $6,985 $1,900 $6,985
-
kWh
-
TOTAL RECOMMENDED $17,273 $5,160 $10,851
42,791
kWh
$6,422
-
MMBtu
TOTAL IMPLEMENTED $7,491 $1,661 $825
9,086
kWh
$6,666
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs