Assessment Year | 1984 |
---|---|
Principal Product | WEB & SHEET FED PRINTING |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $5 M to 10M |
# of Employees | 85 |
Plant Area |
n/a
|
Annual Production | 1,800,000
lb
|
Production Hrs. Annual | 5,550
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $79,877 | 822,098 |
kWh
|
$0.097 |
Natural Gas | $31,239 | 5,013 |
MMBtu
|
$6.23 |
Other Energy | $4,200 | 498 |
MMBtu
|
$8.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,784 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,077 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Paper Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.6121: Burn waste paper for heat | $17,516 | $25,000 | - |
$21,116
-
MMBtu
|
$(-3,600.0)
-
MMBtu
|
- | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $4,173 | - |
$1,594
16,413
kWh
|
$2,579
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,071 | $429 |
$4,071
41,911
kWh
|
- | - | - | |
04 | 2.6121: Reduce hot water temperature to the minimum required | $930 | - |
$826
8,499
kWh
|
$104
-
MMBtu
|
- | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $689 | $745 |
$940
9,672
kWh
|
$(-251.0)
-
MMBtu
|
- | - | |
06 | 2.7441: Replace broken windows and/or window sash | $1,423 | $74 |
$598
6,155
kWh
|
$825
-
MMBtu
|
- | - | |
07 | 2.8223: Add air shields to trucks to increase fuel mileage | $843 | $1,680 | - | - | - |
$843
-
MMBtu
|
|
08 | 2.1123: Install automatic stack damper | $1,582 | $3,625 | - |
$1,582
-
MMBtu
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $228 | $150 |
$228
2,345
kWh
|
- | - | - | |
10 | 2.7492: Use proper thickness of insulation on building envelope | $177 | $100 | - |
$177
-
MMBtu
|
- | - | |
11 | 2.1233: Analyze flue gas for proper air/fuel ratio | $910 | $537 | - |
$910
-
MMBtu
|
- | - | |
12 | 2.3191: Use demand controller or load shedder | $2,900 | $25 |
$2,900
-
kWh
|
- | - | - | |
13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $342 | $32 |
$342
3,517
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $35,784 | $32,397 |
$11,499
88,512
kWh
|
$27,042
-
MMBtu
|
$(-3,600.0)
-
MMBtu
|
$843
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,077 | $1,222 |
$7,659
78,840
kWh
|
$4,418
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Paper Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs