ITAC Assessment: ST0002
ITAC logo
ITAC Assessment: ST0002
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product METAL ELECTRONIC COMPONENTS
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 80
Plant Area
n/a
Annual Production 750,000
pieces
Production Hrs. Annual 3,300
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,354 339,097
kWh
Natural Gas $7,485 1,052
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,194 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,244

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6121: Reduce hot water temperature to the minimum required $306 - $168
1,465
kWh
$138
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,941 $40 $4,941
43,669
kWh
-
03 2.7447: Install vinyl strip / high speed / air curtain doors $845 $80 $285
2,638
kWh
$560
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,150 $310 $2,150
19,050
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $386 $182 $386
3,517
kWh
-
06 2.1233: Analyze flue gas for proper air/fuel ratio $450 $537 - $450
-
MMBtu
07 2.6212: Turn off equipment during breaks, reduce operating time $584 $420 $584
5,275
kWh
-
08 2.6212: Turn off equipment during breaks, reduce operating time $3,455 $1,800 $3,455
30,481
kWh
-
09 2.1123: Install automatic stack damper $564 $282 - $564
-
MMBtu
10 2.6214: Shut off pilots in standby equipment $296 - - $296
-
MMBtu
11 2.2437: Recover waste heat from equipment $147 $370 - $147
-
MMBtu
12 2.7221: Lower temperature during the winter season and vice-versa $2,070 - $1,104
9,672
kWh
$966
-
MMBtu
TOTAL RECOMMENDED $16,194 $4,021 $13,073
115,767
kWh
$3,121
-
MMBtu
TOTAL IMPLEMENTED $15,244 $3,557 $12,687
112,250
kWh
$2,557
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs