ITAC Assessment: SF0497
ITAC logo
ITAC Assessment: SF0497
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Belts
NAICS 326220: Rubber and Plastics Hoses and Belting Manufacturing
SIC 2387: Apparel belts
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 120,000
ft2
Annual Production 2,135,000
units
Production Hrs. Annual 2,080
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $77,872 515,479
kWh
Electricity Demand $33,916 2,533
kW-mo/yr
Natural Gas $4,485 417
MMBtu
TOTAL YEARLY COSTS $116,273
RECOMMENDED SAVINGS* $110,150 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,460

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,521 $70 $1,045
6,920
kWh
$476
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,014 - $2,854
18,893
kWh
- - $(-840.0) -
03 2.7224: Reduce space conditioning during non-working hours $3,873 - $2,382
15,766
kWh
- $1,491
-
MMBtu
- -
04 2.4221: Install compressor air intakes in coolest locations $573 $425 $394
2,610
kWh
$179
-
kW-mo/yr
- - -
05 2.6231: Utilize controls to operate equipment only when needed $807 $1,047 $807
5,344
kWh
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $14,760 $45,819 $10,529
69,698
kWh
$2,640
-
kW-mo/yr
- $1,328 $263
07 2.9114: Use solar heat to make electricty $86,602 $530,610 $70,453
466,360
kWh
$16,149
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $110,150 $577,971 $88,464
585,591
kWh
$19,444
-
kW-mo/yr
$1,491
-
MMBtu
$488 $263
TOTAL IMPLEMENTED $6,460 $425 $5,630
37,269
kWh
$179
-
kW-mo/yr
$1,491
-
MMBtu
$(-840.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs