Assessment Year | 2011 |
---|---|
Principal Product | Fresh Mozzarella |
NAICS | 311513: Cheese Manufacturing |
SIC | 2022: Natural, Processed, and Imitation Cheese |
Sales Range | $50 M to 100M |
# of Employees | 460 |
Plant Area |
50,700
ft2
|
Annual Production | 11,000,000
lb
|
Production Hrs. Annual | 6,080
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $360,826 | 4,765,832 |
kWh
|
$0.076 |
Electricity Demand | $240,706 | 14,238 |
kW-mo/yr
|
$16.91 |
Electricity Fees | $32,924 | - |
|
- |
Natural Gas | $158,640 | 30,906 |
MMBtu
|
$5.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $69,071 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,807 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1212: Operate boilers on high fire setting | $2,708 | - | - | - |
$2,708
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,243 | - |
$2,243
30,108
kWh
|
- | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $257 | $22 |
$170
2,154
kWh
|
$87
-
kW-mo/yr
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $17,934 | $5,426 | - | - |
$17,934
-
MMBtu
|
|
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,812 | $2,778 |
$5,812
78,023
kWh
|
- | - | |
06 | 2.2621: Modify refrigeration system to operate at a lower pressure | $16,688 | $12,500 |
$12,730
170,879
kWh
|
$3,958
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,681 | $5,213 |
$3,962
53,175
kWh
|
$2,719
-
kW-mo/yr
|
- | |
08 | 2.7135: Install occupancy sensors | $697 | $1,356 |
$435
5,844
kWh
|
$262
-
kW-mo/yr
|
- | |
09 | 2.4221: Install compressor air intakes in coolest locations | $483 | $901 |
$268
3,595
kWh
|
$215
-
kW-mo/yr
|
- | |
10 | 2.7132: Install timers on light switches in little used areas | $676 | $1,569 |
$333
4,467
kWh
|
$343
-
kW-mo/yr
|
- | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,910 | $55,222 |
$8,287
111,236
kWh
|
$2,623
-
kW-mo/yr
|
- | |
12 | 2.2437: Recover waste heat from equipment | $3,982 | $20,358 | - | - |
$3,982
-
MMBtu
|
|
TOTAL RECOMMENDED | $69,071 | $105,345 |
$34,240
459,481
kWh
|
$10,207
-
kW-mo/yr
|
$24,624
-
MMBtu
|
||
TOTAL IMPLEMENTED | $21,807 | $8,373 |
$3,181
42,573
kWh
|
$692
-
kW-mo/yr
|
$17,934
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs