| Assessment Year | 1986 |
|---|---|
| Principal Product | CHAINS,NAILS,GREY IRON |
| NAICS |
n/a
|
| SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
n/a
|
| Annual Production | 480,000
lb
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $351,186 | 4,527,550 |
kWh
|
$0.078 |
| Natural Gas | $150,462 | 28,067 |
MMBtu
|
$5.36 |
| Fuel Oil #6 | $470,400 | 93,845 |
MMBtu
|
$5.01 |
| Other Energy | $160,000 | 25,000 |
MMBtu
|
$6.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,073 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,091 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $16,443 | $20,000 |
$21,517
277,550
kWh
|
$(-5,074.0)
-
MMBtu
|
|
| 02 | 2.2514: Cover open tanks | $1,079 | $605 | - |
$1,079
-
MMBtu
|
|
| 03 | 2.4239: Eliminate or reduce compressed air usage | $3,903 | $2,200 |
$3,903
50,410
kWh
|
- | |
| 04 | 2.2136: Install / repair insulation on steam lines | $202 | $140 | - |
$202
-
MMBtu
|
|
| 05 | 2.2135: Repair and eliminate steam leaks | $446 | $30 | - |
$446
-
MMBtu
|
|
| TOTAL RECOMMENDED | $22,073 | $22,975 |
$25,420
327,960
kWh
|
$(-3,347.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $17,091 | $20,170 |
$21,517
277,550
kWh
|
$(-4,426.0)
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs