Assessment Year | 1986 |
---|---|
Principal Product | CHAINS,NAILS,GREY IRON |
NAICS |
n/a
|
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
n/a
|
Annual Production | 480,000
lb
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $351,186 | 4,527,550 |
kWh
|
$0.078 |
Natural Gas | $150,462 | 28,067 |
MMBtu
|
$5.36 |
Fuel Oil #6 | $470,400 | 93,845 |
MMBtu
|
$5.01 |
Other Energy | $160,000 | 25,000 |
MMBtu
|
$6.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,073 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,091 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $16,443 | $20,000 |
$21,517
277,550
kWh
|
$(-5,074.0)
-
MMBtu
|
|
02 | 2.2514: Cover open tanks | $1,079 | $605 | - |
$1,079
-
MMBtu
|
|
03 | 2.4239: Eliminate or reduce compressed air usage | $3,903 | $2,200 |
$3,903
50,410
kWh
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $202 | $140 | - |
$202
-
MMBtu
|
|
05 | 2.2135: Repair and eliminate steam leaks | $446 | $30 | - |
$446
-
MMBtu
|
|
TOTAL RECOMMENDED | $22,073 | $22,975 |
$25,420
327,960
kWh
|
$(-3,347.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $17,091 | $20,170 |
$21,517
277,550
kWh
|
$(-4,426.0)
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs