Assessment Year | 1987 |
---|---|
Principal Product | TUBE & FURNISHING TOOLS |
NAICS |
n/a
|
SIC | 3542: Machine Tools, Metal Forming Types |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $47,264 | 627,491 |
kWh
|
$0.075 |
Natural Gas | $9,086 | 1,801 |
MMBtu
|
$5.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,816 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,993 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $3,496 | $500 |
$3,496
69,754
kWh
|
- | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,497 | - |
$1,497
-
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,823 | $2,986 |
$1,597
26,964
kWh
|
$226 | |
TOTAL RECOMMENDED | $6,816 | $3,486 |
$6,590
96,718
kWh
|
$226 | ||
TOTAL IMPLEMENTED | $4,993 | $500 |
$4,993
69,754
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs