ITAC Assessment: SF0399
ITAC logo
ITAC Assessment: SF0399
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Spices and Frozen Vegetables
NAICS 311411: Frozen Fruit, Juice, and Vegetable Manufacturing
SIC 5142: Packaged Frozen Foods
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 270,000
ft2
Annual Production 23,000,000
lb
Production Hrs. Annual 5,320
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $693,621 11,771,824
kWh
Electricity Demand $380,015 30,600
kW-mo/yr
Electricity Fees $140,208 -
Natural Gas $731,415 141,823
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $273,100 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $100,788

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $14,389 - $4,296
72,937
kWh
- - $10,093
-
MMBtu
02 2.4131: Size electric motors for peak operating efficiency $20,958 $20,025 $10,151
174,019
kWh
$10,807
-
kW-mo/yr
- -
03 2.4221: Install compressor air intakes in coolest locations $1,432 $962 $605
10,275
kWh
$827
-
kW-mo/yr
- -
04 2.4323: Use optimum size and capacity equipment $347 $393 $347
5,895
kWh
- - -
05 2.2437: Recover waste heat from equipment $42,675 $101,238 - - - $42,675
-
MMBtu
06 2.4131: Size electric motors for peak operating efficiency $835 $2,209 $358
6,073
kWh
$477
-
kW-mo/yr
- -
07 2.2511: Insulate bare equipment $1,028 $4,855 - - - $1,028
-
MMBtu
08 2.2621: Modify refrigeration system to operate at a lower pressure $31,982 $112,500 $19,590
332,595
kWh
$12,392
-
kW-mo/yr
- -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $78,758 $307,524 $47,106
799,759
kWh
$23,530
-
kW-mo/yr
$8,122 -
10 2.1243: Use heat from boiler blowdown to preheat boiler feed water $6,800 $37,014 - - - $6,800
-
MMBtu
11 2.4131: Size electric motors for peak operating efficiency $18,286 $77,335 $8,643
146,736
kWh
$9,643
-
kW-mo/yr
- -
12 2.7135: Install occupancy sensors $5,862 $26,604 $3,651
61,993
kWh
$2,211
-
kW-mo/yr
- -
13 2.4131: Size electric motors for peak operating efficiency $11,038 $65,479 $7,480
126,999
kWh
$3,558
-
kW-mo/yr
- -
14 4.212: Adopt in-house material generation $38,710 $49,256 - - $38,710 -
TOTAL RECOMMENDED $273,100 $805,394 $102,227
1,737,281
kWh
$63,445
-
kW-mo/yr
$46,832 $60,596
-
MMBtu
TOTAL IMPLEMENTED $100,788 $335,483 $56,005
950,859
kWh
$26,568
-
kW-mo/yr
$8,122 $10,093
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs