Assessment Year | 2011 |
---|---|
Principal Product | Spices and Frozen Vegetables |
NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 5142: Packaged Frozen Foods |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
270,000
ft2
|
Annual Production | 23,000,000
lb
|
Production Hrs. Annual | 5,320
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $693,621 | 11,771,824 |
kWh
|
$0.059 |
Electricity Demand | $380,015 | 30,600 |
kW-mo/yr
|
$12.42 |
Electricity Fees | $140,208 | - |
|
- |
Natural Gas | $731,415 | 141,823 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $273,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $100,788 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $14,389 | - |
$4,296
72,937
kWh
|
- | - |
$10,093
-
MMBtu
|
|
02 | 2.4131: Size electric motors for peak operating efficiency | $20,958 | $20,025 |
$10,151
174,019
kWh
|
$10,807
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,432 | $962 |
$605
10,275
kWh
|
$827
-
kW-mo/yr
|
- | - | |
04 | 2.4323: Use optimum size and capacity equipment | $347 | $393 |
$347
5,895
kWh
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $42,675 | $101,238 | - | - | - |
$42,675
-
MMBtu
|
|
06 | 2.4131: Size electric motors for peak operating efficiency | $835 | $2,209 |
$358
6,073
kWh
|
$477
-
kW-mo/yr
|
- | - | |
07 | 2.2511: Insulate bare equipment | $1,028 | $4,855 | - | - | - |
$1,028
-
MMBtu
|
|
08 | 2.2621: Modify refrigeration system to operate at a lower pressure | $31,982 | $112,500 |
$19,590
332,595
kWh
|
$12,392
-
kW-mo/yr
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $78,758 | $307,524 |
$47,106
799,759
kWh
|
$23,530
-
kW-mo/yr
|
$8,122 | - | |
10 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $6,800 | $37,014 | - | - | - |
$6,800
-
MMBtu
|
|
11 | 2.4131: Size electric motors for peak operating efficiency | $18,286 | $77,335 |
$8,643
146,736
kWh
|
$9,643
-
kW-mo/yr
|
- | - | |
12 | 2.7135: Install occupancy sensors | $5,862 | $26,604 |
$3,651
61,993
kWh
|
$2,211
-
kW-mo/yr
|
- | - | |
13 | 2.4131: Size electric motors for peak operating efficiency | $11,038 | $65,479 |
$7,480
126,999
kWh
|
$3,558
-
kW-mo/yr
|
- | - | |
14 | 4.212: Adopt in-house material generation | $38,710 | $49,256 | - | - | $38,710 | - | |
TOTAL RECOMMENDED | $273,100 | $805,394 |
$102,227
1,737,281
kWh
|
$63,445
-
kW-mo/yr
|
$46,832 |
$60,596
-
MMBtu
|
||
TOTAL IMPLEMENTED | $100,788 | $335,483 |
$56,005
950,859
kWh
|
$26,568
-
kW-mo/yr
|
$8,122 |
$10,093
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs