Assessment Year | 2011 |
---|---|
Principal Product | Salty Snack Foods |
NAICS | 311919: Other Snack Food Manufacturing |
SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
333,000
ft2
|
Annual Production | 140,000,000
lb
|
Production Hrs. Annual | 8,712
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,630,928 | 25,190,905 |
kWh
|
$0.065 |
Electricity Demand | $782,843 | 44,868 |
kW-mo/yr
|
$17.45 |
Electricity Fees | $37,650 | - |
|
- |
Natural Gas | $3,699,848 | 410,252 |
MMBtu
|
$9.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $298,220 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $153,771 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,251 | - |
$7,251
109,374
kWh
|
- | - | |
02 | 2.2135: Repair and eliminate steam leaks | $4,412 | - | - |
$4,412
-
MMBtu
|
- | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $23,241 | - |
$23,241
349,632
kWh
|
- | - | |
04 | 2.7229: Air condition only space necessary | $4,965 | $424 |
$886
13,365
kWh
|
$4,079
-
MMBtu
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $112,927 | $56,209 |
$112,927
1,703,271
kWh
|
- | - | |
06 | 2.2425: Use flue gases to heat process or service water | $136,531 | $212,500 | - |
$136,531
-
MMBtu
|
- | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $975 | $2,405 |
$975
14,700
kWh
|
- | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $4,046 | $25,868 |
$4,046
61,079
kWh
|
- | - | |
09 | 3.4151: Minimize water usage | $3,872 | $1,867 |
$255
3,838
kWh
|
- |
$3,617
-
Tgal
|
|
TOTAL RECOMMENDED | $298,220 | $299,273 |
$149,581
2,255,259
kWh
|
$145,022
-
MMBtu
|
$3,617
-
Tgal
|
||
TOTAL IMPLEMENTED | $153,771 | $59,038 |
$145,280
2,190,342
kWh
|
$8,491
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs