Assessment Year | 2024 |
---|---|
Principal Product | Plastic Injection Molded Parts |
NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 48 |
Plant Area |
28,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $88,004 | 456,931 |
kWh
|
$0.19 |
Electricity Demand | $31,644 | 1,745 |
kW-mo/yr
|
$18.13 |
Electricity Fees | $2,243 | - |
|
- |
TOTAL YEARLY COSTS | $121,891 | |||
RECOMMENDED SAVINGS* | $98,427 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $11,382 | $8,850 |
$10,403
54,000
kWh
|
$979
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,218 | $7,799 |
$4,218
21,901
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,849 | $5,725 |
$4,793
24,885
kWh
|
$990
-
kW-mo/yr
|
$66 | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,987 | $2,109 |
$2,354
12,220
kWh
|
$633
-
kW-mo/yr
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $23,570 | $42,732 |
$17,123
88,902
kWh
|
$6,447
-
kW-mo/yr
|
- | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $47,700 | $5,600 |
$34,659
179,955
kWh
|
$13,041
-
kW-mo/yr
|
- | |
07 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $2,721 | $5,005 |
$2,187
11,353
kWh
|
$534
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $98,427 | $77,820 |
$75,737
393,216
kWh
|
$22,624
-
kW-mo/yr
|
$66 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs