Assessment Year | 2016 |
---|---|
Principal Product | Die Forged Metals |
NAICS | 332111: Iron and Steel Forging |
SIC | 3462: Iron and Steel Forgings |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
92,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 5,070
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $491,009 | 7,757,934 |
kWh
|
$0.063 |
Electricity Demand | $593,808 | 15,840 |
kW-mo/yr
|
$37.49 |
Electricity Fees | $13,975 | - |
|
- |
Natural Gas | $65,802 | 8,756 |
MMBtu
|
$7.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $323,527 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $90,525 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $140,004 | $382,500 |
$241,457
3,814,483
kWh
|
$275,983
-
kW-mo/yr
|
$(-76,290.0) |
$(-301,146.0)
-
MMBtu
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $47,293 | $24,000 |
$21,237
335,520
kWh
|
$26,056
-
kW-mo/yr
|
- | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $33,404 | $21,190 |
$27,949
441,528
kWh
|
$21,639
-
kW-mo/yr
|
- |
$(-16,184.0)
-
MMBtu
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $27,809 | $31,775 |
$15,242
241,781
kWh
|
$12,567
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,525 | $47,892 |
$10,165
160,581
kWh
|
$15,178
-
kW-mo/yr
|
- | - | $182 | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,423 | $1,500 |
$8,454
133,560
kWh
|
$6,969
-
kW-mo/yr
|
- | - | - | |
07 | 2.6232: Install set-back timers | $14,249 | $344 |
$14,249
225,108
kWh
|
- | - | - | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,558 | $200 |
$13,558
214,208
kWh
|
- | - | - | - | |
09 | 2.7134: Use photocell controls | $2,988 | $1,850 |
$2,988
47,215
kWh
|
- | - | - | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,761 | $1,620 |
$1,167
17,599
kWh
|
$1,594
-
kW-mo/yr
|
- | - | - | |
11 | 2.7135: Install occupancy sensors | $513 | $2,320 |
$513
8,108
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $323,527 | $515,191 |
$356,979
5,639,691
kWh
|
$359,986
-
kW-mo/yr
|
$(-76,290.0) |
$(-317,330.0)
-
MMBtu
|
$182 | ||
TOTAL IMPLEMENTED | $90,525 | $57,275 |
$44,933
710,861
kWh
|
$45,592
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs