ITAC Assessment: SD0355
ITAC logo
ITAC Assessment: SD0355
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product shock and vibration measuring equipment
NAICS 334519: Other Measuring and Controlling Device Manufacturing
SIC 3829: Measuring and Controlling Devices, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 125,000
ft2
Annual Production 0
pieces
Production Hrs. Annual 3,713
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $371,621 3,978,014
kWh
Electricity Demand $156,738 10,765
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,282 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,352

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings
01 2.6231: Utilize controls to operate equipment only when needed $8,531 $1,040 $8,531
91,335
kWh
- - -
02 2.6218: Turn off equipment when not in use $7,397 - $7,397
79,200
kWh
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,058 - $1,058
11,324
kWh
- - -
04 2.4221: Install compressor air intakes in coolest locations $586 $648 $295
3,155
kWh
$291
-
kW-mo/yr
- -
05 2.7135: Install occupancy sensors $897 $700 $897
9,600
kWh
- - -
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $15,253 $18,500 - - - $15,253
-
lb
07 3.3131: Use evaporation to concentrate material $1,560 $1,300 - - $1,560
-
gal
-
TOTAL RECOMMENDED $35,282 $22,188 $18,178
194,614
kWh
$291
-
kW-mo/yr
$1,560
-
gal
$15,253
-
lb
TOTAL IMPLEMENTED $9,352 $700 $9,352
100,124
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs