ITAC Assessment: SD0233
ITAC logo
ITAC Assessment: SD0233
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Plumbing fixtures
NAICS
n/a
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $10
M
to 50
M
# of Employees 145
Plant Area 133,000
ft2
Annual Production 8,000,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $133,211 2,678,781
kWh
Electricity Demand $79,791 8,377
kW-mo/yr
Electricity Fees $3,588 -
Natural Gas $18,202 3,538
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $80,115 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,115

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Primary Product Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $331 $725 $291
5,862
kWh
$40
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,292 $360 $2,840
57,151
kWh
$1,452
-
kW-mo/yr
- - -
03 2.4221: Install compressor air intakes in coolest locations $940 $584 $940
19,050
kWh
- - - -
04 2.2437: Recover waste heat from equipment $1,392 $1,394 - - $1,392
-
MMBtu
- -
05 3.7311: Maintain machines to reduce leaks $6,160 - - - - $6,160
-
lb
-
06 4.446: Automate finishing process $67,000 $9,000 - - - - $67,000
TOTAL RECOMMENDED $80,115 $12,063 $4,071
82,063
kWh
$1,492
-
kW-mo/yr
$1,392
-
MMBtu
$6,160
-
lb
$67,000
TOTAL IMPLEMENTED $13,115 $3,063 $4,071
82,063
kWh
$1,492
-
kW-mo/yr
$1,392
-
MMBtu
$6,160
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs