| Assessment Year | 1999 |
|---|---|
| Principal Product | Plumbing fixtures |
| NAICS |
n/a
|
| SIC | 3432: Plumbing Fixture Fittings and Trim |
| Sales Range | $10 M to 50M |
| # of Employees | 145 |
| Plant Area |
133,000
ft2
|
| Annual Production | 8,000,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $133,211 | 2,678,781 |
kWh
|
$0.050 |
| Electricity Demand | $79,791 | 8,377 |
kW-mo/yr
|
$9.53 |
| Electricity Fees | $3,588 | - |
|
- |
| Natural Gas | $18,202 | 3,538 |
MMBtu
|
$5.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $80,115 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,115 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $331 | $725 |
$291
5,862
kWh
|
$40
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,292 | $360 |
$2,840
57,151
kWh
|
$1,452
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $940 | $584 |
$940
19,050
kWh
|
- | - | - | - | |
| 04 | 2.2437: Recover waste heat from equipment | $1,392 | $1,394 | - | - |
$1,392
-
MMBtu
|
- | - | |
| 05 | 3.7311: Maintain machines to reduce leaks | $6,160 | - | - | - | - |
$6,160
-
lb
|
- | |
| 06 | 4.446: Automate finishing process | $67,000 | $9,000 | - | - | - | - | $67,000 | |
| TOTAL RECOMMENDED | $80,115 | $12,063 |
$4,071
82,063
kWh
|
$1,492
-
kW-mo/yr
|
$1,392
-
MMBtu
|
$6,160
-
lb
|
$67,000 | ||
| TOTAL IMPLEMENTED | $13,115 | $3,063 |
$4,071
82,063
kWh
|
$1,492
-
kW-mo/yr
|
$1,392
-
MMBtu
|
$6,160
-
lb
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs