ITAC Assessment: SD0192
ITAC logo
ITAC Assessment: SD0192
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Prefabricated Buildings
NAICS
n/a
SIC 3448: Prefabricated Metal Buildings and Components
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 2,800
ft2
Annual Production 2,000
pieces
Production Hrs. Annual 4,208
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $69,359 906,800
kWh
Electricity Demand $25,601 3,121
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $80,057 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $44,008

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,498 $1,550 $7,285
94,666
kWh
$2,213
-
kW-mo/yr
- -
02 2.7261: Install timers and/or thermostats $1,473 $600 $1,473
19,050
kWh
- - -
03 2.4221: Install compressor air intakes in coolest locations $491 $221 $491
6,448
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $17,631 $13,030 $13,584
176,436
kWh
$4,047
-
kW-mo/yr
- -
05 2.7144: Install spectral reflectors / delamp $2,099 $1,980 $1,443
18,757
kWh
$656
-
kW-mo/yr
- -
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,880 $5,000 - - - $2,880
07 3.5311: Recover and reuse waste material $11,900 $60 - - $11,900
-
gal
-
08 4.112: Replace old machine with new automatic multi-station tool $15,149 $5,000 - - - $15,149
09 4.122: Develop standard procedures to improve internal yields $15,149 - - - - $15,149
10 4.421: Modify current incentive program $3,787 - - - - $3,787
TOTAL RECOMMENDED $80,057 $27,441 $24,276
315,357
kWh
$6,916
-
kW-mo/yr
$11,900
-
gal
$36,965
TOTAL IMPLEMENTED $44,008 $21,620 $22,312
289,859
kWh
$6,916
-
kW-mo/yr
$11,900
-
gal
$2,880
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs