Assessment Year | 1997 |
---|---|
Principal Product | Aerospace safety equipment; mechanical flight control compon |
NAICS |
n/a
|
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
95,000
ft2
|
Annual Production | 219,000
lb
|
Production Hrs. Annual | 4,674
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $164,075 | 2,326,495 |
kWh
|
$0.071 |
Electricity Demand | $47,582 | 5,726 |
kW-mo/yr
|
$8.31 |
Natural Gas | $2,757 | 437 |
MMBtu
|
$6.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $88,960 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $79,447 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,269 | $940 |
$914
12,603
kWh
|
$355
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7261: Install timers and/or thermostats | $5,192 | $4,200 |
$5,192
73,271
kWh
|
- | - | - | - | - | |
03 | 2.4226: Use / purchase optimum sized compressor | $4,767 | $5,600 |
$4,485
63,306
kWh
|
$282
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,093 | $6,000 |
$1,295
18,171
kWh
|
$1,894
-
kW-mo/yr
|
$(-96.0)
-
MMBtu
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,239 | $8,727 |
$3,260
46,014
kWh
|
$979
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7144: Install spectral reflectors / delamp | $8,038 | $12,145 |
$5,590
78,839
kWh
|
$2,448
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $2,285 | $902 |
$1,545
21,688
kWh
|
$740
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4314: Use synthetic lubricant | $6,420 | - | - | - | - |
$6,420
-
gal
|
- | - | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,420 | - | - | - | - | - |
$4,420
-
lb
|
- | |
10 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,341 | $2,000 | - | - | - | - | - | $3,341 | |
11 | 4.421: Modify current incentive program | $4,675 | $4,800 | - | - | - | - | - | $4,675 | |
12 | 4.652: Replace existing equipment with more suitable substitutes | $41,221 | $200 | - | - | - | - | - | $41,221 | |
TOTAL RECOMMENDED | $88,960 | $45,514 |
$22,281
313,892
kWh
|
$6,698
-
kW-mo/yr
|
$(-96.0)
-
MMBtu
|
$6,420
-
gal
|
$4,420
-
lb
|
$49,237 | ||
TOTAL IMPLEMENTED | $79,447 | $39,514 |
$20,986
295,721
kWh
|
$4,804
-
kW-mo/yr
|
- | - |
$4,420
-
lb
|
$49,237 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs