Assessment Year | 1994 |
---|---|
Principal Product | Folding Cartons, Corrgated Boxes, 2-piece Rigid Box |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
100,000
ft2
|
Annual Production | 3,000
ton
|
Production Hrs. Annual | 3,940
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,618 | 473,329 |
kWh
|
$0.12 |
Natural Gas | $8,737 | 1,137 |
MMBtu
|
$7.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,866 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,002 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $5,687 | $4,560 |
$5,687
46,307
kWh
|
- | |
02 | 2.2511: Insulate bare equipment | $71 | $60 |
$71
586
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $9,229 | $10,500 |
$9,229
80,012
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,322 | $2,887 |
$3,322
28,429
kWh
|
- | |
05 | 2.7144: Install spectral reflectors / delamp | $5,445 | $6,175 |
$5,445
43,669
kWh
|
- | |
06 | 2.7135: Install occupancy sensors | $1,165 | $800 |
$1,165
9,379
kWh
|
- | |
07 | 2.7132: Install timers on light switches in little used areas | $1,235 | $760 |
$1,235
9,672
kWh
|
- | |
08 | 2.7261: Install timers and/or thermostats | $1,712 | $400 |
$829
7,327
kWh
|
$883
-
MMBtu
|
|
TOTAL RECOMMENDED | $27,866 | $26,142 |
$26,983
225,381
kWh
|
$883
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,002 | $9,822 |
$10,002
81,770
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs