| Assessment Year | 2001 |
|---|---|
| Principal Product | Material handling cranes & monrail systems |
| NAICS |
n/a
|
| SIC | 3536: Overhead Traveling Cranes, Hoists, and Monorail Systems |
| Sales Range | $5 M to 10M |
| # of Employees | 60 |
| Plant Area |
95,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $46,539 | 529,500 |
kWh
|
$0.088 |
| Electricity Demand | $17,209 | 2,483 |
kW-mo/yr
|
$6.93 |
| Natural Gas | $29,724 | 3,250 |
MMBtu
|
$9.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $9,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,249 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,581 | $2,500 | - |
$2,581
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,252 | - |
$3,610
41,068
kWh
|
$1,642
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $769 | $135 |
$437
4,975
kWh
|
$332
-
kW-mo/yr
|
- | |
| 04 | 2.6212: Turn off equipment during breaks, reduce operating time | $480 | - |
$170
1,939
kWh
|
$310
-
kW-mo/yr
|
- | |
| 05 | 2.2522: Isolate hot or cold equipment | $339 | $1,615 | - | - |
$339
-
MMBtu
|
|
| TOTAL RECOMMENDED | $9,421 | $4,250 |
$4,217
47,982
kWh
|
$4,865
-
kW-mo/yr
|
$339
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,249 | $135 |
$607
6,914
kWh
|
$642
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs