Assessment Year | 1993 |
---|---|
Principal Product | FROZEN SPECIALTIES |
NAICS |
n/a
|
SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 2
Tgal
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $202,590 | 1,991,208 |
kWh
|
$0.10 |
Natural Gas | $23,338 | 5,689 |
MMBtu
|
$4.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,149 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,734 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $218 | $260 |
$218
2,052
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,098 | $120 |
$2,098
20,516
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,480 | $1,600 |
$2,649
26,084
kWh
|
$(-169.0) | |
04 | 2.7144: Install spectral reflectors / delamp | $2,975 | $4,280 |
$2,733
26,964
kWh
|
$242 | |
05 | 2.6232: Install set-back timers | $1,642 | $2,320 |
$1,626
16,120
kWh
|
$16 | |
06 | 2.7134: Use photocell controls | $415 | $230 |
$363
3,517
kWh
|
$52 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $48 | $35 |
$36
293
kWh
|
$12 | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $892 | $147 |
$1,100
10,844
kWh
|
$(-208.0) | |
09 | 2.7261: Install timers and/or thermostats | $381 | $300 |
$381
8,206
kWh
|
- | |
TOTAL RECOMMENDED | $11,149 | $9,292 |
$11,204
114,596
kWh
|
$(-55.0) | ||
TOTAL IMPLEMENTED | $10,734 | $9,062 |
$10,841
111,079
kWh
|
$(-107.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs