ITAC Assessment: OK0541
ITAC logo
ITAC Assessment: OK0541
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Pumps, compressors, valves
NAICS
n/a
SIC 3563: Air and Gas Compressors
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 42,000
ft2
Annual Production 17,500
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,393 1,785,756
kWh
Electricity Demand $107,683 10,833
kW-mo/yr
Natural Gas $12,151 2,888
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $66,892 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,262

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,363 $5,833 $2,146
79,132
kWh
$1,217
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,554 $1,917 $1,006
35,756
kWh
$548
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $894 - $894
42,790
kWh
- - -
04 2.7135: Install occupancy sensors $759 $516 $759
28,136
kWh
- - -
05 2.4221: Install compressor air intakes in coolest locations $443 $99 $369
13,482
kWh
$74
-
kW-mo/yr
- -
06 4.513: Re-arrange equipment layout to reduce labor costs $48,000 $15,312 - - - $48,000
07 3.5316: Contract a wood pallet recycling company $10,080 - - - $10,080
-
lb
-
08 3.4155: Meter waste water $1,317 - - - - $1,317
09 3.5315: Lease / purchase baler; sell cardboard to recycler $352 - - - $352
-
lb
-
10 3.6192: Use a less expensive method of waste removal $130 - - - $130
-
lb
-
TOTAL RECOMMENDED $66,892 $23,677 $5,174
199,296
kWh
$1,839
-
kW-mo/yr
$10,562
-
lb
$49,317
TOTAL IMPLEMENTED $63,262 $21,244 $3,409
135,404
kWh
$1,291
-
kW-mo/yr
$10,562
-
lb
$48,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs