ITAC Assessment: LE0449
ITAC logo
ITAC Assessment: LE0449
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product LAN Communication Cables
NAICS 335929: Other Communication and Energy Wire Manufacturing
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $100
M
to 500
M
# of Employees 150
Plant Area 300,000
ft2
Annual Production 700,000
units
Production Hrs. Annual 7,488
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,305,374 24,192,000
kWh
Electricity Demand $75,631 45,449
kW-mo/yr
Electricity Fees $28,183 -
Natural Gas $91,942 9,146
MMBtu
TOTAL YEARLY COSTS $1,501,130
RECOMMENDED SAVINGS* $335,966 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,895

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,357 $1,000 $6,058
112,188
kWh
$299
-
kW-mo/yr
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $7,677 $2,850 $7,238
134,065
kWh
$439
-
kW-mo/yr
03 2.4221: Install compressor air intakes in coolest locations $3,339 $3,500 $3,120
57,783
kWh
$219
-
kW-mo/yr
04 2.7232: Replace existing hvac unit with high efficiency model $298,212 $362,400 $295,783
5,477,472
kWh
$2,429
-
kW-mo/yr
05 2.6212: Turn off equipment during breaks, reduce operating time $14,930 $20,000 $12,370
229,089
kWh
$2,560
-
kW-mo/yr
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,078 $3,780 $1,980
36,661
kWh
$98
-
kW-mo/yr
07 2.7135: Install occupancy sensors $913 $2,750 $913
16,907
kWh
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $945 $4,252 $835
15,466
kWh
$110
-
kW-mo/yr
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,515 $6,962 $1,397
25,876
kWh
$118
-
kW-mo/yr
TOTAL RECOMMENDED $335,966 $407,494 $329,694
6,105,507
kWh
$6,272
-
kW-mo/yr
TOTAL IMPLEMENTED $10,895 $15,994 $10,270
190,191
kWh
$625
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs