| Assessment Year | 1993 |
|---|---|
| Principal Product | PUNCH AND SALAD DRESSING |
| NAICS |
n/a
|
| SIC | 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
n/a
|
| Annual Production | 1,000,000
pieces
|
| Production Hrs. Annual | 6,248
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $36,510 | 280,481 |
kWh
|
$0.13 |
| Natural Gas | $11,537 | 1,945 |
MMBtu
|
$5.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,252 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,796 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $110 | $142 |
$110
879
kWh
|
- | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $263 | $20 |
$263
2,052
kWh
|
- | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $217 | $117 | - |
$217
-
MMBtu
|
- | |
| 04 | 2.2122: Install / repair insulation on condensate lines | $193 | $108 | - |
$193
-
MMBtu
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,432 | - |
$1,502
11,430
kWh
|
- | $(-70.0) | |
| 06 | 2.7144: Install spectral reflectors / delamp | $3,237 | $2,680 |
$3,207
24,619
kWh
|
- | $30 | |
| 07 | 2.6232: Install set-back timers | $1,003 | $1,160 |
$913
7,034
kWh
|
- | $90 | |
| 08 | 2.7134: Use photocell controls | $650 | $345 |
$615
4,689
kWh
|
- | $35 | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $345 | $19 |
$290
2,345
kWh
|
- | $55 | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $173 | - |
$91
586
kWh
|
- | $82 | |
| 11 | 2.7261: Install timers and/or thermostats | $629 | $200 |
$420
3,224
kWh
|
$209
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $8,252 | $4,791 |
$7,411
56,858
kWh
|
$619
-
MMBtu
|
$222 | ||
| TOTAL IMPLEMENTED | $7,796 | $4,663 |
$7,148
54,806
kWh
|
$426
-
MMBtu
|
$222 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs