ITAC Assessment: DL0207
ITAC logo
ITAC Assessment: DL0207
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Large metal structures
NAICS 335313: Switchgear and Switchboard Apparatus Manufacturing
SIC 3613: Switchgear and Switchboard Apparatus
Sales Range $1
M
to 5
M
# of Employees 47
Plant Area 40,000
ft2
Annual Production 200
units
Production Hrs. Annual 3,000
hrs
Location (State) Delaware

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,632 472,559
kWh
Electricity Demand $11,287 1,470
kW-mo/yr
Electricity Fees $8,798 -
Natural Gas $15,021 1,720
MMBtu
Waste Disposal Costs
Water Usage $9,308 461
Tgal
TOTAL YEARLY COSTS $83,046
RECOMMENDED SAVINGS* $19,610 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,700

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.6231: Utilize controls to operate equipment only when needed $2,027 - $1,522
18,568
kWh
$428
-
kW-mo/yr
$77
-
MMBtu
02 2.6231: Utilize controls to operate equipment only when needed $383 $315 $299
3,651
kWh
$84
-
kW-mo/yr
-
03 2.6231: Utilize controls to operate equipment only when needed $182 - $69
838
kWh
$19
-
kW-mo/yr
$94
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $100 $400 $78
957
kWh
$22
-
kW-mo/yr
-
05 2.4239: Eliminate or reduce compressed air usage $557 $1,000 $435
5,308
kWh
$122
-
kW-mo/yr
-
06 2.4239: Eliminate or reduce compressed air usage $2,522 $1,016 $1,970
24,020
kWh
$552
-
kW-mo/yr
-
07 2.2437: Recover waste heat from equipment $801 $449 - - $801
-
MMBtu
08 2.7234: Use heat pump for space conditioning $3,608 $4,012 $2,818
34,363
kWh
$790
-
kW-mo/yr
-
09 2.7226: Use computer programs to optimize hvac performance $2,543 $6,428 $1,269
15,481
kWh
$356
-
kW-mo/yr
$918
-
MMBtu
10 2.7142: Utilize higher efficiency lamps and/or ballasts $3,800 $6,208 $3,027
36,912
kWh
$773
-
kW-mo/yr
-
11 2.2511: Insulate bare equipment $797 $2,124 - - $797
-
MMBtu
12 2.7243: Improve air circulation with destratification fans / other methods $298 $1,434 - - $298
-
MMBtu
13 2.1134: Eliminate leaks in combustible gas lines $1,993 $2,500 - - $1,993
-
MMBtu
TOTAL RECOMMENDED $19,610 $25,886 $11,487
140,098
kWh
$3,145
-
kW-mo/yr
$4,978
-
MMBtu
TOTAL IMPLEMENTED $11,700 $11,173 $6,954
84,808
kWh
$1,875
-
kW-mo/yr
$2,871
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs