ITAC Assessment: KU0100
ITAC logo
ITAC Assessment: KU0100
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product ANIMAL AND POULTRY FEED
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $10
M
to 50
M
# of Employees 82
Plant Area
n/a
Annual Production 180,000
ton
Production Hrs. Annual 6,128
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $320,770 5,418,816
kWh
Natural Gas $280,367 67,295
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $65,520 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,005 $4,164 $10,005
169,109
kWh
-
02 2.1243: Use heat from boiler blowdown to preheat boiler feed water $3,578 $10,000 - $3,578
-
MMBtu
03 2.1233: Analyze flue gas for proper air/fuel ratio $4,770 $2,400 - $4,770
-
MMBtu
04 2.2414: Use waste heat from hot flue gases to preheat $5,967 $10,000 - $5,967
-
MMBtu
05 2.2122: Install / repair insulation on condensate lines $41,200 $41,500 - $41,200
-
MMBtu
TOTAL RECOMMENDED $65,520 $68,064 $10,005
169,109
kWh
$55,515
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs