ITAC Assessment: SD0061
ITAC logo
ITAC Assessment: SD0061
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product TRAFFIC CONTROL SIGNALS
NAICS
n/a
SIC 3669: Communications Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area
n/a
Annual Production 20,000
pieces
Production Hrs. Annual 4,334
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $237,140 2,385,991
kWh
Natural Gas $30,327 5,025
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,964 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $648 $827 $648
6,448
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,078 $100 $2,078
20,809
kWh
- -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $12,414 - $12,414
-
kWh
- -
04 2.2514: Cover open tanks $5,954 $284 $5,954
59,789
kWh
- -
05 2.2511: Insulate bare equipment $1,375 $85 $1,375
13,775
kWh
- -
06 2.2511: Insulate bare equipment $189 $54 - $189
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $598 - $657
6,741
kWh
- $(-59.0)
08 2.7144: Install spectral reflectors / delamp $2,069 $3,080 $1,711
17,292
kWh
- $358
09 2.7142: Utilize higher efficiency lamps and/or ballasts $682 $855 $682
3,224
kWh
- -
10 2.6232: Install set-back timers $2,033 $2,400 $1,737
17,585
kWh
- $296
11 2.7134: Use photocell controls $6,945 $4,000 $6,790
68,288
kWh
- $155
12 2.7261: Install timers and/or thermostats $2,979 $300 $2,115
21,395
kWh
$864
-
MMBtu
-
TOTAL RECOMMENDED $37,964 $11,985 $36,161
235,346
kWh
$1,053
-
MMBtu
$750
TOTAL IMPLEMENTED $17,000 $5,296 $16,845
169,109
kWh
- $155
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs