Assessment Year | 1993 |
---|---|
Principal Product | TRAFFIC CONTROL SIGNALS |
NAICS |
n/a
|
SIC | 3669: Communications Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
n/a
|
Annual Production | 20,000
pieces
|
Production Hrs. Annual | 4,334
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $237,140 | 2,385,991 |
kWh
|
$0.099 |
Natural Gas | $30,327 | 5,025 |
MMBtu
|
$6.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,964 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $648 | $827 |
$648
6,448
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,078 | $100 |
$2,078
20,809
kWh
|
- | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $12,414 | - |
$12,414
-
kWh
|
- | - | |
04 | 2.2514: Cover open tanks | $5,954 | $284 |
$5,954
59,789
kWh
|
- | - | |
05 | 2.2511: Insulate bare equipment | $1,375 | $85 |
$1,375
13,775
kWh
|
- | - | |
06 | 2.2511: Insulate bare equipment | $189 | $54 | - |
$189
-
MMBtu
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $598 | - |
$657
6,741
kWh
|
- | $(-59.0) | |
08 | 2.7144: Install spectral reflectors / delamp | $2,069 | $3,080 |
$1,711
17,292
kWh
|
- | $358 | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $682 | $855 |
$682
3,224
kWh
|
- | - | |
10 | 2.6232: Install set-back timers | $2,033 | $2,400 |
$1,737
17,585
kWh
|
- | $296 | |
11 | 2.7134: Use photocell controls | $6,945 | $4,000 |
$6,790
68,288
kWh
|
- | $155 | |
12 | 2.7261: Install timers and/or thermostats | $2,979 | $300 |
$2,115
21,395
kWh
|
$864
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $37,964 | $11,985 |
$36,161
235,346
kWh
|
$1,053
-
MMBtu
|
$750 | ||
TOTAL IMPLEMENTED | $17,000 | $5,296 |
$16,845
169,109
kWh
|
- | $155 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs