ITAC Assessment: SD0055
ITAC logo
ITAC Assessment: SD0055
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product PLASTIC BOTTLES
NAICS
n/a
SIC 3085: Plastics Bottles
Sales Range $10
M
to 50
M
# of Employees 131
Plant Area
n/a
Annual Production 9,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $817,345 10,894,197
kWh
Natural Gas $7,554 1,255
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,438 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,595

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $1,575 $1,822 $1,575
21,102
kWh
- -
02 2.7261: Install timers and/or thermostats $2,135 $300 $1,779
23,740
kWh
$356
-
MMBtu
-
03 2.6223: Schedule use of elevators to conserve energy $4,262 $236 $4,262
56,858
kWh
- -
04 2.6212: Turn off equipment during breaks, reduce operating time $6,447 - $6,447
85,873
kWh
- -
05 2.2511: Insulate bare equipment $152 $56 $152
2,052
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $132 - $168
2,345
kWh
- $(-36.0)
07 2.7144: Install spectral reflectors / delamp $1,601 $3,800 $1,380
18,464
kWh
- $221
08 2.6232: Install set-back timers $1,134 $1,600 $934
12,309
kWh
- $200
TOTAL RECOMMENDED $17,438 $7,814 $16,697
222,743
kWh
$356
-
MMBtu
$385
TOTAL IMPLEMENTED $5,595 $5,978 $5,054
67,703
kWh
$356
-
MMBtu
$185
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs