ITAC Assessment: SD0045
ITAC logo
ITAC Assessment: SD0045
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product FROZEN CITR,FRUIT JUICES
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $50
M
to 100
M
# of Employees 260
Plant Area
n/a
Annual Production 18,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,388,209 16,457,210
kWh
Natural Gas $168,346 49,877
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $94,087 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $94,087

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $6,714 $6,185 $6,714
79,719
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $14,975 $19,672 $14,975
177,608
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $13,104 $80 $13,104
155,334
kWh
- -
04 2.6231: Utilize controls to operate equipment only when needed $846 $1,200 $846
14,361
kWh
- -
05 2.2122: Install / repair insulation on condensate lines $14,356 $3,980 - $14,356
-
MMBtu
-
06 2.2113: Repair or replace steam traps $4,682 $750 - $4,682
-
MMBtu
-
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $16,668 - $16,668
-
kWh
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $9,464 - $10,093
119,578
kWh
- $(-629.0)
09 2.7144: Install spectral reflectors / delamp $8,119 $7,640 $7,041
83,236
kWh
- $1,078
10 2.7142: Utilize higher efficiency lamps and/or ballasts $3,643 - $2,567
30,481
kWh
- $1,076
11 2.7261: Install timers and/or thermostats $1,516 $600 $1,516
17,878
kWh
- -
TOTAL RECOMMENDED $94,087 $40,107 $73,524
678,195
kWh
$19,038
-
MMBtu
$1,525
TOTAL IMPLEMENTED $94,087 $40,107 $73,524
678,195
kWh
$19,038
-
MMBtu
$1,525
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs