Assessment Year | 1993 |
---|---|
Principal Product | FROZEN CITR,FRUIT JUICES |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $50 M to 100M |
# of Employees | 260 |
Plant Area |
n/a
|
Annual Production | 18,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,388,209 | 16,457,210 |
kWh
|
$0.084 |
Natural Gas | $168,346 | 49,877 |
MMBtu
|
$3.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $94,087 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $94,087 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $6,714 | $6,185 |
$6,714
79,719
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $14,975 | $19,672 |
$14,975
177,608
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,104 | $80 |
$13,104
155,334
kWh
|
- | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $846 | $1,200 |
$846
14,361
kWh
|
- | - | |
05 | 2.2122: Install / repair insulation on condensate lines | $14,356 | $3,980 | - |
$14,356
-
MMBtu
|
- | |
06 | 2.2113: Repair or replace steam traps | $4,682 | $750 | - |
$4,682
-
MMBtu
|
- | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $16,668 | - |
$16,668
-
kWh
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,464 | - |
$10,093
119,578
kWh
|
- | $(-629.0) | |
09 | 2.7144: Install spectral reflectors / delamp | $8,119 | $7,640 |
$7,041
83,236
kWh
|
- | $1,078 | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,643 | - |
$2,567
30,481
kWh
|
- | $1,076 | |
11 | 2.7261: Install timers and/or thermostats | $1,516 | $600 |
$1,516
17,878
kWh
|
- | - | |
TOTAL RECOMMENDED | $94,087 | $40,107 |
$73,524
678,195
kWh
|
$19,038
-
MMBtu
|
$1,525 | ||
TOTAL IMPLEMENTED | $94,087 | $40,107 |
$73,524
678,195
kWh
|
$19,038
-
MMBtu
|
$1,525 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs