ITAC Assessment: SD0033
ITAC logo
ITAC Assessment: SD0033
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PLASTIC PELLETS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area
n/a
Annual Production 60,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $362,343 5,342,907
kWh
Natural Gas $193,560 33,869
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,369 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $3,066 $12,195 $3,066
45,135
kWh
- -
02 2.7261: Install timers and/or thermostats $2,962 $20 $2,962
43,669
kWh
- -
03 2.2444: Use hot process fluids to preheat incoming process fluids $11,846 $4,000 - $11,846
-
MMBtu
-
04 2.2414: Use waste heat from hot flue gases to preheat $5,532 $3,500 - $5,532
-
MMBtu
-
05 2.6232: Install set-back timers $673 $200 $537
7,913
kWh
- $136
06 2.7142: Utilize higher efficiency lamps and/or ballasts $107 $713 $224
11,137
kWh
- $(-117.0)
07 2.6232: Install set-back timers $2,727 $2,560 $2,284
33,705
kWh
- $443
08 2.7142: Utilize higher efficiency lamps and/or ballasts $2,456 $2,200 $310
4,689
kWh
- $2,146
TOTAL RECOMMENDED $29,369 $25,388 $9,383
146,248
kWh
$17,378
-
MMBtu
$2,608
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs