| Assessment Year | 1992 |
|---|---|
| Principal Product | PLASTIC BAGS AND BOTTLES |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 173 |
| Plant Area |
n/a
|
| Annual Production | 10,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $182,697 | 2,901,817 |
kWh
|
$0.063 |
| Natural Gas | $384 | 55 |
MMBtu
|
$6.98 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,301 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,301 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $978 | $1,000 |
$978
15,533
kWh
|
- | - | |
| 02 | 2.7261: Install timers and/or thermostats | $2,832 | $200 |
$1,581
25,205
kWh
|
$1,251
-
MMBtu
|
- | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $4,982 | $350 |
$4,982
79,132
kWh
|
- | - | |
| 04 | 2.2691: Shut off cooling if cold outside air will cool process | $4,723 | $499 |
$4,723
75,029
kWh
|
- | - | |
| 05 | 2.2511: Insulate bare equipment | $941 | $71 |
$941
14,947
kWh
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $178 | $175 |
$92
1,465
kWh
|
- | $86 | |
| 07 | 2.6232: Install set-back timers | $1,004 | $2,880 |
$849
13,482
kWh
|
- | $155 | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,663 | $2,420 |
$314
4,982
kWh
|
- | $1,349 | |
| TOTAL RECOMMENDED | $17,301 | $7,595 |
$14,460
229,775
kWh
|
$1,251
-
MMBtu
|
$1,590 | ||
| TOTAL IMPLEMENTED | $17,301 | $7,595 |
$14,460
229,775
kWh
|
$1,251
-
MMBtu
|
$1,590 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs