ITAC Assessment: MI0314
ITAC logo
ITAC Assessment: MI0314
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Chocolate Bars
NAICS 311351: Chocolate and Confectionery Manufacturing from Cacao Beans
SIC 2066: Chocolate and Cocoa Products
Sales Range $5
M
to 10
M
# of Employees 57
Plant Area 45,000
ft2
Annual Production 900
ton
Production Hrs. Annual 2,340
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,535 1,734,400
kWh
Electricity Demand $51,775 4,948
kW-mo/yr
Electricity Fees $20,970 -
TOTAL YEARLY COSTS $156,280
RECOMMENDED SAVINGS* $37,153 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,415

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7425: Clean or color roof to reduce solar load $8,333 $6,560 $6,417
133,693
kWh
$1,916
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,727 $1,660 $3,412
71,081
kWh
$3,315
-
kW-mo/yr
03 2.7496: Install partitions to reduce size of conditioned space $5,444 $3,600 $4,192
87,584
kWh
$1,252
-
kW-mo/yr
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,595 $12,009 $2,170
45,199
kWh
$2,425
-
kW-mo/yr
05 2.7293: Install dry sprinkler system or other method to reduce heating requirements $4,033 $12,706 $3,102
64,619
kWh
$931
-
kW-mo/yr
06 2.7447: Install vinyl strip / high speed / air curtain doors $3,364 $1,125 $2,590
53,965
kWh
$774
-
kW-mo/yr
07 2.7447: Install vinyl strip / high speed / air curtain doors $2,023 $1,885 $1,558
32,456
kWh
$465
-
kW-mo/yr
08 2.7447: Install vinyl strip / high speed / air curtain doors $1,679 $290 $1,209
25,180
kWh
$470
-
kW-mo/yr
09 2.7135: Install occupancy sensors $518 $466 $518
10,790
kWh
-
10 2.7134: Use photocell controls $437 $240 $206
4,296
kWh
$231
-
kW-mo/yr
TOTAL RECOMMENDED $37,153 $40,541 $25,374
528,863
kWh
$11,779
-
kW-mo/yr
TOTAL IMPLEMENTED $23,415 $23,584 $16,578
345,621
kWh
$6,837
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs