ITAC Assessment: RU0161
ITAC logo
ITAC Assessment: RU0161
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product FANS,BLOWERS FOR ELECTRIC MOTORS
NAICS
n/a
SIC 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 60,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $95,169 975,088
kWh
Natural Gas $23,779 4,608
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,378 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,393

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.6232: Install set-back timers $689 $100 $689
7,034
kWh
- -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,622 $5,125 $1,622
16,706
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,075 $183 $1,258
12,896
kWh
- $(-183.0)
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,363 - $3,363
34,584
kWh
- -
05 2.2136: Install / repair insulation on steam lines $157 $60 - $157
-
MMBtu
-
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $8,472 $2,500 $8,472
-
kWh
- -
TOTAL RECOMMENDED $15,378 $7,968 $15,404
71,220
kWh
$157
-
MMBtu
$(-183.0)
TOTAL IMPLEMENTED $10,393 $2,843 $10,419
19,930
kWh
$157
-
MMBtu
$(-183.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs