Assessment Year | 1992 |
---|---|
Principal Product | FANS,BLOWERS FOR ELECTRIC MOTORS |
NAICS |
n/a
|
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
n/a
|
Annual Production | 60,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $95,169 | 975,088 |
kWh
|
$0.098 |
Natural Gas | $23,779 | 4,608 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,378 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,393 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $689 | $100 |
$689
7,034
kWh
|
- | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,622 | $5,125 |
$1,622
16,706
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,075 | $183 |
$1,258
12,896
kWh
|
- | $(-183.0) | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,363 | - |
$3,363
34,584
kWh
|
- | - | |
05 | 2.2136: Install / repair insulation on steam lines | $157 | $60 | - |
$157
-
MMBtu
|
- | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,472 | $2,500 |
$8,472
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $15,378 | $7,968 |
$15,404
71,220
kWh
|
$157
-
MMBtu
|
$(-183.0) | ||
TOTAL IMPLEMENTED | $10,393 | $2,843 |
$10,419
19,930
kWh
|
$157
-
MMBtu
|
$(-183.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs