| Assessment Year | 1993 |
|---|---|
| Principal Product | Refined Waxes |
| NAICS |
n/a
|
| SIC | 3533: Oil and Gas Field Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
n/a
|
| Annual Production | 48,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $435,482 | 11,274,619 |
kWh
|
$0.039 |
| Natural Gas | $1,943,555 | 917,532 |
MMBtu
|
$2.12 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $412,297 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $409,096 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2113: Repair or replace steam traps | $170,442 | - | - |
$170,442
-
MMBtu
|
|
| 02 | 2.2121: Increase amount of condensate returned | $126,322 | $90,000 | - |
$126,322
-
MMBtu
|
|
| 03 | 2.2113: Repair or replace steam traps | $106,473 | $4,025 | - |
$106,473
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,188 | $4,152 |
$5,188
119,578
kWh
|
- | |
| 05 | 2.2437: Recover waste heat from equipment | $3,201 | $7,220 | - |
$3,201
-
MMBtu
|
|
| 06 | 2.2136: Install / repair insulation on steam lines | $671 | $866 | - |
$671
-
MMBtu
|
|
| TOTAL RECOMMENDED | $412,297 | $106,263 |
$5,188
119,578
kWh
|
$407,109
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $409,096 | $99,043 |
$5,188
119,578
kWh
|
$403,908
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs