ITAC Assessment: OK0422
ITAC logo
ITAC Assessment: OK0422
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Refined Waxes
NAICS
n/a
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area
n/a
Annual Production 48,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $435,482 11,274,619
kWh
Natural Gas $1,943,555 917,532
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $412,297 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $409,096

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2113: Repair or replace steam traps $170,442 - - $170,442
-
MMBtu
02 2.2121: Increase amount of condensate returned $126,322 $90,000 - $126,322
-
MMBtu
03 2.2113: Repair or replace steam traps $106,473 $4,025 - $106,473
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,188 $4,152 $5,188
119,578
kWh
-
05 2.2437: Recover waste heat from equipment $3,201 $7,220 - $3,201
-
MMBtu
06 2.2136: Install / repair insulation on steam lines $671 $866 - $671
-
MMBtu
TOTAL RECOMMENDED $412,297 $106,263 $5,188
119,578
kWh
$407,109
-
MMBtu
TOTAL IMPLEMENTED $409,096 $99,043 $5,188
119,578
kWh
$403,908
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs