ITAC Assessment: RU0157
ITAC logo
ITAC Assessment: RU0157
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product DENTAL DRILLS AND BITS
NAICS
n/a
SIC 3843: Dental Equipment and Supplies
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area
n/a
Annual Production 55,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $144,432 1,978,019
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,855 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,007 - $5,007
68,581
kWh
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $3,668 - $3,668
50,410
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,010 $359 $5,369
73,564
kWh
$(-359.0)
04 2.2511: Insulate bare equipment $1,752 $292 $1,752
24,033
kWh
-
05 2.7111: Reduce illumination to minimum necessary levels $5,637 - $5,637
77,374
kWh
-
06 2.7261: Install timers and/or thermostats $2,781 $478 $2,781
38,101
kWh
-
TOTAL RECOMMENDED $23,855 $1,129 $24,214
332,063
kWh
$(-359.0)
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs