ITAC Assessment: RU0136
ITAC logo
ITAC Assessment: RU0136
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PLASTIC BAGS
NAICS
n/a
SIC 2673: Plastics, Foil, and Coated Paper Bags
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area
n/a
Annual Production 15,000,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $352,420 4,271,981
kWh
Natural Gas $411,061 80,732
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,352 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,543

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,772 - $4,772
57,737
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,508 $8,097 $7,708
93,494
kWh
- $(-1,200.0)
03 2.4221: Install compressor air intakes in coolest locations $498 $152 $498
6,155
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,771 $30 $3,771
42,790
kWh
- -
05 2.1233: Analyze flue gas for proper air/fuel ratio $2,803 $500 - $2,803
-
MMBtu
-
TOTAL RECOMMENDED $18,352 $8,779 $16,749
200,176
kWh
$2,803
-
MMBtu
$(-1,200.0)
TOTAL IMPLEMENTED $8,543 $30 $8,543
100,527
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs