| Assessment Year | 1991 |
|---|---|
| Principal Product | PLASTIC BAGS |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 90 |
| Plant Area |
n/a
|
| Annual Production | 3,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $185,745 | 1,930,539 |
kWh
|
$0.096 |
| Natural Gas | $12,442 | 1,760 |
MMBtu
|
$7.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,465 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,465 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,350 | - |
$1,350
14,068
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $2,064 | $87 |
$2,064
21,395
kWh
|
- | |
| 03 | 2.4312: Improve lubrication practices | $1,353 | $800 |
$1,353
14,068
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,855 | $201 |
$1,855
16,706
kWh
|
- | |
| 05 | 2.7243: Improve air circulation with destratification fans / other methods | $1,087 | $6,840 |
$(-722.0)
(-7,620)
kWh
|
$1,809
-
MMBtu
|
|
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,343 | - |
$4,343
45,135
kWh
|
- | |
| 07 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,041 | $2,700 |
$2,041
21,395
kWh
|
- | |
| 08 | 2.4237: Substitute compressed air cooling with water or air cooling | $5,372 | $875 |
$5,372
55,979
kWh
|
- | |
| TOTAL RECOMMENDED | $19,465 | $11,503 |
$17,656
181,126
kWh
|
$1,809
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $19,465 | $11,503 |
$17,656
181,126
kWh
|
$1,809
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs