ITAC Assessment: RU0104
ITAC logo
ITAC Assessment: RU0104
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product PUTTY KNIVES & SCRAPERS
NAICS
n/a
SIC 3423: Hand and Edge Tools, Except Machine Tools and Handsaws
Sales Range $50
M
to 100
M
# of Employees 135
Plant Area
n/a
Annual Production 12,000,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $299,765 3,502,052
kWh
Natural Gas $52,485 9,142
MMBtu
Fuel Oil #4 $8,377 1,872
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,702 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,706

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $592 - $592
7,034
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $513 $419 $513
6,155
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,006 $630 $2,006
23,447
kWh
-
04 2.2514: Cover open tanks $433 $500 - $433
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,477 - $1,477
17,292
kWh
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $996 $1,250 $996
11,723
kWh
-
07 2.1311: Replace electrically-operated equipment with fossil fuel equipment $20,685 $63,000 $26,821
313,306
kWh
$(-6,136.0)
-
MMBtu
TOTAL RECOMMENDED $26,702 $65,799 $32,405
378,957
kWh
$(-5,703.0)
-
MMBtu
TOTAL IMPLEMENTED $25,706 $64,549 $31,409
367,234
kWh
$(-5,703.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs