| Assessment Year | 1990 |
|---|---|
| Principal Product | PUTTY KNIVES & SCRAPERS |
| NAICS |
n/a
|
| SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
| Sales Range | $50 M to 100M |
| # of Employees | 135 |
| Plant Area |
n/a
|
| Annual Production | 12,000,000
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $299,765 | 3,502,052 |
kWh
|
$0.086 |
| Natural Gas | $52,485 | 9,142 |
MMBtu
|
$5.74 |
| Fuel Oil #4 | $8,377 | 1,872 |
MMBtu
|
$4.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,702 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $25,706 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $592 | - |
$592
7,034
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $513 | $419 |
$513
6,155
kWh
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,006 | $630 |
$2,006
23,447
kWh
|
- | |
| 04 | 2.2514: Cover open tanks | $433 | $500 | - |
$433
-
MMBtu
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,477 | - |
$1,477
17,292
kWh
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $996 | $1,250 |
$996
11,723
kWh
|
- | |
| 07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $20,685 | $63,000 |
$26,821
313,306
kWh
|
$(-6,136.0)
-
MMBtu
|
|
| TOTAL RECOMMENDED | $26,702 | $65,799 |
$32,405
378,957
kWh
|
$(-5,703.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $25,706 | $64,549 |
$31,409
367,234
kWh
|
$(-5,703.0)
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs