ITAC Assessment: RU0102
ITAC logo
ITAC Assessment: RU0102
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product FIRE & INTRUSION SYSTEMS
NAICS
n/a
SIC 3669: Communications Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 370
Plant Area
n/a
Annual Production 650,000
pieces
Production Hrs. Annual 4,720
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $252,340 2,898,886
kWh
Natural Gas $17,917 3,319
MMBtu
Fuel Oil #2 $2,205 281
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,192 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,441

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $504 - $504
5,862
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,462 $631 $2,462
28,136
kWh
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,881 $2,500 $5,881
-
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $632 $302 $632
7,327
kWh
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,466 - $4,466
51,290
kWh
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $917 - $917
10,551
kWh
-
07 2.7492: Use proper thickness of insulation on building envelope $9,330 $34,669 $4,755
54,807
kWh
$4,575
-
MMBtu
TOTAL RECOMMENDED $24,192 $38,102 $19,617
157,973
kWh
$4,575
-
MMBtu
TOTAL IMPLEMENTED $13,441 $3,433 $13,441
86,753
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs