Assessment Year | 1990 |
---|---|
Principal Product | FIRE & INTRUSION SYSTEMS |
NAICS |
n/a
|
SIC | 3669: Communications Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 370 |
Plant Area |
n/a
|
Annual Production | 650,000
pieces
|
Production Hrs. Annual | 4,720
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $252,340 | 2,898,886 |
kWh
|
$0.087 |
Natural Gas | $17,917 | 3,319 |
MMBtu
|
$5.40 |
Fuel Oil #2 | $2,205 | 281 |
MMBtu
|
$7.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,192 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,441 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $504 | - |
$504
5,862
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,462 | $631 |
$2,462
28,136
kWh
|
- | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,881 | $2,500 |
$5,881
-
kWh
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $632 | $302 |
$632
7,327
kWh
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,466 | - |
$4,466
51,290
kWh
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $917 | - |
$917
10,551
kWh
|
- | |
07 | 2.7492: Use proper thickness of insulation on building envelope | $9,330 | $34,669 |
$4,755
54,807
kWh
|
$4,575
-
MMBtu
|
|
TOTAL RECOMMENDED | $24,192 | $38,102 |
$19,617
157,973
kWh
|
$4,575
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,441 | $3,433 |
$13,441
86,753
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs