ITAC Assessment: RU0100
ITAC logo
ITAC Assessment: RU0100
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product FABRICATED WIRE PRODUCTS
NAICS
n/a
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $50
M
to 100
M
# of Employees 135
Plant Area
n/a
Annual Production 4,700,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,918 1,066,823
kWh
Natural Gas $9,724 1,900
MMBtu
Fuel Oil #4 $19,632 5,184
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,512 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,512

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #4 Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $410 - $410
4,396
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $431 $419 $431
4,689
kWh
-
03 2.2511: Insulate bare equipment $3,924 $5,255 - $3,924
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,447 - $1,447
15,826
kWh
-
05 2.6212: Turn off equipment during breaks, reduce operating time $4,300 $239 - $4,300
-
MMBtu
TOTAL RECOMMENDED $10,512 $5,913 $2,288
24,911
kWh
$8,224
-
MMBtu
TOTAL IMPLEMENTED $10,512 $5,913 $2,288
24,911
kWh
$8,224
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs