Assessment Year | 1990 |
---|---|
Principal Product | INSULATION VAPOR BARRIER |
NAICS |
n/a
|
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
n/a
|
Annual Production | 450
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $217,413 | 2,659,730 |
kWh
|
$0.082 |
Fuel Oil #2 | $162,847 | 31,304 |
MMBtu
|
$5.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,353 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,615 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,594 | $2,500 |
$3,594
43,962
kWh
|
- | - | |
02 | 2.2136: Install / repair insulation on steam lines | $2,404 | $72 | - |
$2,404
-
MMBtu
|
- | |
03 | 2.2135: Repair and eliminate steam leaks | $4,881 | - | - |
$4,881
-
MMBtu
|
- | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,156 | $375 | - |
$4,156
-
MMBtu
|
- | |
05 | 2.2122: Install / repair insulation on condensate lines | $454 | $269 | - |
$454
-
MMBtu
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,859 | - |
$2,859
34,877
kWh
|
- | - | |
07 | 2.4322: Use or replace with energy efficient substitutes | $865 | $584 |
$865
10,551
kWh
|
- | - | |
08 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $3,140 | $4,878 |
$3,182
38,980
kWh
|
- | $(-42.0) | |
TOTAL RECOMMENDED | $22,353 | $8,678 |
$10,500
128,370
kWh
|
$11,895
-
MMBtu
|
$(-42.0) | ||
TOTAL IMPLEMENTED | $11,615 | $7,378 |
$6,776
82,942
kWh
|
$4,881
-
MMBtu
|
$(-42.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs