| Assessment Year | 1990 |
|---|---|
| Principal Product | INSULATION VAPOR BARRIER |
| NAICS |
n/a
|
| SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 65 |
| Plant Area |
n/a
|
| Annual Production | 450
thousand feet
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $217,413 | 2,659,730 |
kWh
|
$0.082 |
| Fuel Oil #2 | $162,847 | 31,304 |
MMBtu
|
$5.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,353 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,615 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,594 | $2,500 |
$3,594
43,962
kWh
|
- | - | |
| 02 | 2.2136: Install / repair insulation on steam lines | $2,404 | $72 | - |
$2,404
-
MMBtu
|
- | |
| 03 | 2.2135: Repair and eliminate steam leaks | $4,881 | - | - |
$4,881
-
MMBtu
|
- | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,156 | $375 | - |
$4,156
-
MMBtu
|
- | |
| 05 | 2.2122: Install / repair insulation on condensate lines | $454 | $269 | - |
$454
-
MMBtu
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,859 | - |
$2,859
34,877
kWh
|
- | - | |
| 07 | 2.4322: Use or replace with energy efficient substitutes | $865 | $584 |
$865
10,551
kWh
|
- | - | |
| 08 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $3,140 | $4,878 |
$3,182
38,980
kWh
|
- | $(-42.0) | |
| TOTAL RECOMMENDED | $22,353 | $8,678 |
$10,500
128,370
kWh
|
$11,895
-
MMBtu
|
$(-42.0) | ||
| TOTAL IMPLEMENTED | $11,615 | $7,378 |
$6,776
82,942
kWh
|
$4,881
-
MMBtu
|
$(-42.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs