ITAC Assessment: RU0093
ITAC logo
ITAC Assessment: RU0093
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product CONVEYERS & CHUTES
NAICS
n/a
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area
n/a
Annual Production 1,250
ton
Production Hrs. Annual 2,600
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,969 1,388,042
kWh
Fuel Oil #2 $27,092 4,620
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,725 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,308

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,497 $183 $1,497
16,413
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $651 - $651
7,034
kWh
- -
03 2.7243: Improve air circulation with destratification fans / other methods $4,109 $1,900 $(-321.0)
(-3,517)
kWh
- $4,430
-
MMBtu
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,811 $2,500 $3,811
-
kWh
- -
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $4,019 - $5,217
57,444
kWh
$(-1,198.0)
-
MMBtu
-
06 2.7447: Install vinyl strip / high speed / air curtain doors $227 $550 - - $227
-
MMBtu
07 2.7492: Use proper thickness of insulation on building envelope $5,411 $1,920 - - $5,411
-
MMBtu
TOTAL RECOMMENDED $19,725 $7,053 $10,855
77,374
kWh
$(-1,198.0)
-
MMBtu
$10,068
-
MMBtu
TOTAL IMPLEMENTED $5,308 $2,683 $5,308
16,413
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs