Assessment Year | 1990 |
---|---|
Principal Product | CONVEYERS & CHUTES |
NAICS |
n/a
|
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
n/a
|
Annual Production | 1,250
ton
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $125,969 | 1,388,042 |
kWh
|
$0.091 |
Fuel Oil #2 | $27,092 | 4,620 |
MMBtu
|
$5.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,725 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,308 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,497 | $183 |
$1,497
16,413
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $651 | - |
$651
7,034
kWh
|
- | - | |
03 | 2.7243: Improve air circulation with destratification fans / other methods | $4,109 | $1,900 |
$(-321.0)
(-3,517)
kWh
|
- |
$4,430
-
MMBtu
|
|
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,811 | $2,500 |
$3,811
-
kWh
|
- | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,019 | - |
$5,217
57,444
kWh
|
$(-1,198.0)
-
MMBtu
|
- | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $227 | $550 | - | - |
$227
-
MMBtu
|
|
07 | 2.7492: Use proper thickness of insulation on building envelope | $5,411 | $1,920 | - | - |
$5,411
-
MMBtu
|
|
TOTAL RECOMMENDED | $19,725 | $7,053 |
$10,855
77,374
kWh
|
$(-1,198.0)
-
MMBtu
|
$10,068
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,308 | $2,683 |
$5,308
16,413
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs