| Assessment Year | 1990 |
|---|---|
| Principal Product | HEADERS,ARC SHIELDS, ETC |
| NAICS |
n/a
|
| SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
n/a
|
| Annual Production | 60,000,000
pieces
|
| Production Hrs. Annual | 6,400
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $345,378 | 4,184,056 |
kWh
|
$0.083 |
| Natural Gas | $51,353 | 10,527 |
MMBtu
|
$4.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,384 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,222 | $9,000 |
$8,222
99,062
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,858 | $68 |
$1,858
22,274
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,918 | $650 |
$7,918
95,545
kWh
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,016 | - |
$3,016
36,342
kWh
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $2,717 | $3,492 |
$2,717
32,825
kWh
|
- | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,877 | $1,200 | - |
$1,877
-
MMBtu
|
|
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $626 | $170 | - |
$626
-
MMBtu
|
|
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $150 | $500 | - |
$150
-
MMBtu
|
|
| TOTAL RECOMMENDED | $26,384 | $15,080 |
$23,731
286,048
kWh
|
$2,653
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs