| Assessment Year | 1990 |
|---|---|
| Principal Product | LIGHTING FIXTURES |
| NAICS |
n/a
|
| SIC | 3646: Commercial, Industrial, and Institutional Electric Lighting Fixtures |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 300,000
pieces
|
| Production Hrs. Annual | 1,950
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $61,317 | 608,441 |
kWh
|
$0.10 |
| Natural Gas | $35,575 | 7,115 |
MMBtu
|
$5.00 |
| Fuel Oil #2 | $28,575 | 5,919 |
MMBtu
|
$4.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,078 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,842 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $251 | $102 |
$251
2,638
kWh
|
- | - | |
| 02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,842 | - |
$1,842
18,171
kWh
|
- | - | |
| 03 | 2.6218: Turn off equipment when not in use | $3,507 | - |
$3,507
35,170
kWh
|
- | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $1,019 | $1,880 | - | - |
$1,019
-
MMBtu
|
|
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $3,583 | $12,800 | - |
$3,583
-
MMBtu
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $487 | - |
$487
4,982
kWh
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,389 | $650 |
$2,389
23,740
kWh
|
- | - | |
| TOTAL RECOMMENDED | $13,078 | $15,432 |
$8,476
84,701
kWh
|
$3,583
-
MMBtu
|
$1,019
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,842 | - |
$1,842
18,171
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs