ITAC Assessment: RU0073
ITAC logo
ITAC Assessment: RU0073
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product STEEL DISPLAY SHELVES
NAICS
n/a
SIC 2542: Office and Store Fixtures, Partitions, Shelving, and Lockers, Except Wood
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area
n/a
Annual Production 75,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,988 631,008
kWh
Natural Gas $38,703 7,259
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,104 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,271

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,457 $450 $2,457
20,516
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,131 $325 $4,131
34,584
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,227 $2,028 $1,227
10,258
kWh
-
04 2.7229: Air condition only space necessary $846 - $846
7,034
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $1,635 $645 $1,635
13,775
kWh
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $278 - $278
2,345
kWh
-
07 2.2437: Recover waste heat from equipment $3,530 $44,000 - $3,530
-
MMBtu
TOTAL RECOMMENDED $14,104 $47,448 $10,574
88,512
kWh
$3,530
-
MMBtu
TOTAL IMPLEMENTED $7,271 $2,998 $7,271
60,962
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs