| Assessment Year | 1989 |
|---|---|
| Principal Product | TEFLON-COATED METAL |
| NAICS |
n/a
|
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 150 |
| Plant Area |
n/a
|
| Annual Production | 40
thousand feet
|
| Production Hrs. Annual | 4,240
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $44,031 | 475,967 |
kWh
|
$0.093 |
| Natural Gas | $100,461 | 22,245 |
MMBtu
|
$4.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,282 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,307 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $422 | $134 |
$422
4,396
kWh
|
- | |
| 02 | 2.2511: Insulate bare equipment | $1,836 | $682 | - |
$1,836
-
MMBtu
|
|
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,698 | - |
$2,698
29,015
kWh
|
- | |
| 04 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $4,001 | $8,500 | - |
$4,001
-
MMBtu
|
|
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $2,552 | $6,800 | - |
$2,552
-
MMBtu
|
|
| 06 | 2.2153: Close off unneeded steam lines | $1,773 | $1,880 | - |
$1,773
-
MMBtu
|
|
| TOTAL RECOMMENDED | $13,282 | $17,996 |
$3,120
33,411
kWh
|
$10,162
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $6,307 | $2,562 |
$2,698
29,015
kWh
|
$3,609
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs