| Assessment Year | 2006 |
|---|---|
| Principal Product | Aluminum beverage cans |
| NAICS | 332431: Metal Can Manufacturing |
| SIC | 3411: Metal Cans |
| Sales Range | $10 M to 50M |
| # of Employees | 115 |
| Plant Area |
250,000
ft2
|
| Annual Production | 1,800,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,034,240 | 33,777,524 |
kWh
|
$0.031 |
| Electricity Demand | $694,102 | 49,508 |
kW-mo/yr
|
$14.02 |
| Electricity Fees | $1,589 | - |
|
- |
| Natural Gas | $994,103 | 137,213 |
MMBtu
|
$7.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $302,440 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $52,290 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $213,730 | $703,800 |
$150,150
3,226,200
kWh
|
$63,580
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 4.123: Reduce defects by reducing product tipping | $31,500 | $1,420 | - | - | - | - | $31,500 | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $5,120 | $4,920 | - | - |
$5,120
-
MMBtu
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,990 | $200 |
$1,430
30,700
kWh
|
$560
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $480 | $165 |
$345
7,424
kWh
|
$135
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $34,970 | $37,470 |
$24,860
534,200
kWh
|
$9,000
-
kW-mo/yr
|
- | $240 | - | $870 | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,400 | $9,510 |
$5,770
123,900
kWh
|
$1,900
-
kW-mo/yr
|
- | $310 | - | $1,420 | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,800 | $2,380 |
$2,330
50,200
kWh
|
$1,160
-
kW-mo/yr
|
- | $60 | - | $250 | |
| 09 | 2.9114: Use solar heat to make electricty | $1,450 | $18,370 |
$650
14,050
kWh
|
$800
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $302,440 | $778,235 |
$185,535
3,986,674
kWh
|
$77,135
-
kW-mo/yr
|
$5,120
-
MMBtu
|
$610 | $31,500 | $2,540 | ||
| TOTAL IMPLEMENTED | $52,290 | $18,595 |
$9,875
212,224
kWh
|
$3,755
-
kW-mo/yr
|
$5,120
-
MMBtu
|
$370 | $31,500 | $1,670 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs