ITAC Assessment: CO0583
ITAC logo
ITAC Assessment: CO0583
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Aluminum beverage cans
NAICS 332431: Metal Can Manufacturing
SIC 3411: Metal Cans
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area 250,000
ft2
Annual Production 1,800,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,034,240 33,777,524
kWh
Electricity Demand $694,102 49,508
kW-mo/yr
Electricity Fees $1,589 -
Natural Gas $994,103 137,213
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $302,440 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $52,290

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $213,730 $703,800 $150,150
3,226,200
kWh
$63,580
-
kW-mo/yr
- - - -
02 4.123: Reduce defects by reducing product tipping $31,500 $1,420 - - - - $31,500 -
03 2.2136: Install / repair insulation on steam lines $5,120 $4,920 - - $5,120
-
MMBtu
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,990 $200 $1,430
30,700
kWh
$560
-
kW-mo/yr
- - - -
05 2.4133: Use most efficient type of electric motors $480 $165 $345
7,424
kWh
$135
-
kW-mo/yr
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $34,970 $37,470 $24,860
534,200
kWh
$9,000
-
kW-mo/yr
- $240 - $870
07 2.7142: Utilize higher efficiency lamps and/or ballasts $9,400 $9,510 $5,770
123,900
kWh
$1,900
-
kW-mo/yr
- $310 - $1,420
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,800 $2,380 $2,330
50,200
kWh
$1,160
-
kW-mo/yr
- $60 - $250
09 2.9114: Use solar heat to make electricty $1,450 $18,370 $650
14,050
kWh
$800
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $302,440 $778,235 $185,535
3,986,674
kWh
$77,135
-
kW-mo/yr
$5,120
-
MMBtu
$610 $31,500 $2,540
TOTAL IMPLEMENTED $52,290 $18,595 $9,875
212,224
kWh
$3,755
-
kW-mo/yr
$5,120
-
MMBtu
$370 $31,500 $1,670
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs