| Assessment Year | 1988 |
|---|---|
| Principal Product | HOUSEHOLD PRODUCTS |
| NAICS |
n/a
|
| SIC | 2841: Soap and Other Detergents, Except Specialty Cleaners |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
n/a
|
| Annual Production | 5,000
Tgal
|
| Production Hrs. Annual | 4,335
hrs
|
| Location (State) | Maryland |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $126,138 | 2,056,858 |
kWh
|
$0.061 |
| Natural Gas | $87,032 | 18,269 |
MMBtu
|
$4.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,410 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $25,864 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,773 | - |
$4,773
78,253
kWh
|
- | |
| 02 | 2.7243: Improve air circulation with destratification fans / other methods | $6,546 | $7,020 |
$(-486.0)
(-7,913)
kWh
|
$7,032
-
MMBtu
|
|
| 03 | 2.4312: Improve lubrication practices | $298 | $800 |
$298
4,982
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,890 | $678 |
$2,890
47,479
kWh
|
- | |
| 05 | 2.2164: Turn off steam tracing during mild weather | $9,235 | - | - |
$9,235
-
MMBtu
|
|
| 06 | 2.7261: Install timers and/or thermostats | $4,858 | $1,195 | - |
$4,858
-
MMBtu
|
|
| 07 | 2.2511: Insulate bare equipment | $2,812 | $384 |
$2,812
46,014
kWh
|
- | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $998 | $500 | - |
$998
-
MMBtu
|
|
| TOTAL RECOMMENDED | $32,410 | $10,577 |
$10,287
168,815
kWh
|
$22,123
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $25,864 | $3,557 |
$10,773
176,728
kWh
|
$15,091
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs