Assessment Year | 2011 |
---|---|
Principal Product | Motors |
NAICS | 333612: Speed Changer, Industrial High-Speed Drive, and Gear Manufacturing |
SIC | 3566: Speed Changers, Industrial High-Speed Drives, and Gears |
Sales Range | $100 M to 500M |
# of Employees | 390 |
Plant Area |
225,000
ft2
|
Annual Production | 480,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,010,822 | 22,147,200 |
kWh
|
$0.046 |
Natural Gas | $124,845 | 24,442 |
MMBtu
|
$5.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $121,259 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $46,568 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $20,409 | $71,773 |
$20,409
443,664
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $245 | $1,488 |
$245
5,320
kWh
|
- | |
03 | 2.7135: Install occupancy sensors | $391 | $456 |
$391
8,504
kWh
|
- | |
04 | 2.7122: Disconnect ballasts | $481 | $921 |
$481
10,452
kWh
|
- | |
05 | 2.6218: Turn off equipment when not in use | $17,462 | - |
$17,462
379,600
kWh
|
- | |
06 | 2.7241: Install outside air damper / economizer on hvac unit | $13,197 | $9,150 |
$13,197
286,902
kWh
|
- | |
07 | 2.7232: Replace existing hvac unit with high efficiency model | $17,005 | $315,900 |
$17,005
369,672
kWh
|
- | |
08 | 2.1224: Replace boiler | $26,135 | $24,220 | - |
$26,135
-
MMBtu
|
|
09 | 2.2414: Use waste heat from hot flue gases to preheat | $4,244 | $11,700 | - |
$4,244
-
MMBtu
|
|
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,037 | - |
$18,037
392,098
kWh
|
- | |
11 | 2.4221: Install compressor air intakes in coolest locations | $1,760 | $1,338 |
$1,760
38,250
kWh
|
- | |
12 | 2.2511: Insulate bare equipment | $1,893 | $2,263 | - |
$1,893
-
MMBtu
|
|
TOTAL RECOMMENDED | $121,259 | $439,209 |
$88,987
1,934,462
kWh
|
$32,272
-
MMBtu
|
||
TOTAL IMPLEMENTED | $46,568 | $27,502 |
$20,433
444,172
kWh
|
$26,135
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs