ITAC Assessment: RU0005
ITAC logo
ITAC Assessment: RU0005
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product THERMO-PLASTIC PARTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 160
Plant Area
n/a
Annual Production 18,013,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $371,198 4,496,776
kWh
Natural Gas $18,919 3,064
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,109 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,623

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,958 $184 $1,958
23,740
kWh
-
02 2.2511: Insulate bare equipment $791 $84 $791
9,672
kWh
-
03 2.2511: Insulate bare equipment $6,186 $292 $6,186
74,443
kWh
-
04 2.4321: Upgrade obsolete equipment $1,486 - $1,486
17,878
kWh
-
05 2.7442: Keep doors and windows shut when not on use $2,688 - - $2,688
-
MMBtu
TOTAL RECOMMENDED $13,109 $560 $10,421
125,733
kWh
$2,688
-
MMBtu
TOTAL IMPLEMENTED $11,623 $560 $8,935
107,855
kWh
$2,688
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs